Skip To Main Content

Solar PPA

Project 5698

Updates

  • 10.23.2026 - Racking completed. AC/DC equipment installation completed.
  • 10.16.2026 - Racking installed. AC/DC equipment install. 
  • 10.09.2026 - Racking installed at approximately 40% at all schools. Disconnects and inverters have been installed at all elementary schools. Currently installing inverters at Princeton Middle School. 
wiring

 

wiring

 

roof racking

 

inverters and electrical gear

 

  • 10.01.2026 - DC wiring is ongoing at all schools. Installing DC and AC equipment at many of the schools. Coordination is ongoing at PHS and will be finalized early next week.
solar

 

solar

 

  • 9.25.2026 - Racking completed at Johnson Park, Community Park, Littlebrook, Riverside, and Princeton Middle School. Currently installing racking at Princeton High School.  
racking

 

racking

 

  • 9.18.2026 - Community Park: Installation of racking has begun on the front roof. Johnson Park: Installation of racking has begun. Littlebrook: Materials loaded and racking has begun. 
solar

 

solar

 

  • 9.11.2026 - Community Park: Loaded with racking materials & installation of racking has begun on the front roof. Johnson Park: Loaded with racking materials & installation of racking has begun.
  • 9.3.2026 - Material was delivered for all schools. Mobilization will begin 9.8.26.
  • 8.27.2026 - Material will be arriving on 9.1.26. Mobilization will begin on 9.8.26. Engineered plans have been issued for final approval by Architect. All permits from utility and Municipality have been issued.
  • 8.21.2026 - Pre-construction meeting was held. Final designs are being distributed to architects. Logistic plans are being sent over for approval. 
  • 8.15.2026 - Pre-construction meeting is scheduled for Thursday 8.20.26. Final design will be issued by Friday 8.14.26.
  • 7.31.2026 - Pre-construction meetings are scheduled. Electrical walk through will take place next week for tie in locations.
  • 7.23.2026 - Engineering meetings were held, and work should begin within the next 2 weeks.
  • 7.17.2026 - Executed power purchase agreement was received. Coordination meetings are being held with HVAC contractors and PPS facilities.
  • 7.10.2026 - The final contract has been received and engineering is ongoing. 
  • 7.3.2026 - Engineering is ongoing. Applications for permits are being issued to town.
  • 6.26.2026 - Solar program engineering is under way.
  • 6.1.2026 - Surveys for the roof and steel supports will begin this week and engineering will be finalized. Work is scheduled to begin after 6/22/2026.
  • Solar designs are in progress for coordination at all schools