10.09.2026 - Racking installed at approximately 40% at all schools. Disconnects and inverters have been installed at all elementary schools. Currently installing inverters at Princeton Middle School.
10.01.2026 - DC wiring is ongoing at all schools. Installing DC and AC equipment at many of the schools. Coordination is ongoing at PHS and will be finalized early next week.
9.25.2026 - Racking completed at Johnson Park, Community Park, Littlebrook, Riverside, and Princeton Middle School. Currently installing racking at Princeton High School.
9.18.2026 - Community Park: Installation of racking has begun on the front roof. Johnson Park: Installation of racking has begun. Littlebrook: Materials loaded and racking has begun.
9.11.2026 - Community Park: Loaded with racking materials & installation of racking has begun on the front roof. Johnson Park: Loaded with racking materials & installation of racking has begun.
9.3.2026 - Material was delivered for all schools. Mobilization will begin 9.8.26.
8.27.2026 - Material will be arriving on 9.1.26. Mobilization will begin on 9.8.26. Engineered plans have been issued for final approval by Architect. All permits from utility and Municipality have been issued.
8.21.2026 - Pre-construction meeting was held. Final designs are being distributed to architects. Logistic plans are being sent over for approval.
8.15.2026 - Pre-construction meeting is scheduled for Thursday 8.20.26. Final design will be issued by Friday 8.14.26.
7.31.2026 - Pre-construction meetings are scheduled. Electrical walk through will take place next week for tie in locations.
7.23.2026 - Engineering meetings were held, and work should begin within the next 2 weeks.
7.17.2026 - Executed power purchase agreement was received. Coordination meetings are being held with HVAC contractors and PPS facilities.
7.10.2026 - The final contract has been received and engineering is ongoing.
7.3.2026 - Engineering is ongoing. Applications for permits are being issued to town.
6.26.2026 - Solar program engineering is under way.
6.1.2026 - Surveys for the roof and steel supports will begin this week and engineering will be finalized. Work is scheduled to begin after 6/22/2026.
Solar designs are in progress for coordination at all schools