Site Improvements/Upgrades (Various Schools)
Project 5559a
Project Overview
| Littlebrook | Johnson Park | Riverside |
|---|---|---|
![]()
|
![]()
|
![]()
|
|
|
|
Updates
-
10.16.2026 - Johnson Park: Construction complete.
-
10.01.2026 - Johnson Park: Pouring concrete stairs, assembling basketball hoops for install. Seeding and hay.

-
9.25.2026 - Johnson Park: Footings are underway for the concrete steps.
![]()
|
![]()
|
-
9.18.2026 - Johnson Park: Footings are underway for the concrete steps.
-
9.11.2026 - Johnson Park: Retaining wall is complete. Pathway was installed to the upper play area. Basketball striping is completed. Riverside: 3 pickleball courts installed & project completed. Littlebrook: Project completed.
![]()
|
![]()
|
-
9.3.2026 - Johnson Park: Finish retaining walls, begin regrading and reseeding of old work areas. Littlebrook: Rain Garden is being installed.

-
8.27.2026 - Johnson Park: Retaining wall is almost complete. Inlets have been installed to new basin. Demolished and reconstructed the new amphitheater. Littlebrook: Asphalt truck path installed. Retention basin back filled.

-
8.21.2026 - Johnson Park: Basin installed and backfilled, multiple inlets along backside of school installed, working on grading for stairs and retaining wall. Littlebrook: All piping installed and outflow structure backfilled. Asphalt paving area installed. Retention basin back filled. Riverside: Asphalt play area complete.

-
8.15.2026 - Johnson Park: Digging and Installation of water basin. Installation of inlets in upper play area. Installation of drainage system and mulch in upper play area. Beginning renovation work in exterior amphitheater. Littlebrook: All piping installed and outflow structure backfilled. Repaving asphalt play area today. Riverside: Milled and repaved asphalt play area.
-
8.06.2026 - Johnson Park: Retaining wall drawings are finalized. Retention basin is being installed. Engineered fiber mulch has been installed at the lower playground as well as the upper playground. Littebrook: Bio retention Basin will begin next week, as well as Completing the retention basin. Asphalt playground is scheduled to be paved on Tuesday. Riverside: Parking lot is milled and will be paved next Tuesday

- 7.31.2026 - Littlebrook: Continuing with storm lines and structures, testing has been ongoing, and backfill of the retention system will begin early next week.
- 7.23.2026 - Johnson Park: Footings for retaining wall are underway. Existing mulch has been removed and will be installed next week.
Littlebrook: Storm tech basin system has been installed and being completed. Storm utility lines are being installed and existing structure raised to new elevation.

- 7.17.2026 - Johnson Park: Stoned has been laid down over existing basin.
Littlebrook: Storm tech basins are being installed. - 7.10.2026 - Johnson Park: Storm tech was delivered for new installed filter fabric and clean ¾ stone at existing basin. Continued demolition of existing retaining walls.
Littlebrook: Storm tech basins were dropped off.

- 6.26.2026 - Johnson Park: Demolition of retaining wall and trench drain was removed. Existing mulch is in process of being removed.
Littlebrook: Construction fence was installed today. Milling of the playground will start Monday
-
6.1.2026 - Logistic and staging plans have been developed and submittals are going in. Third part inspections were awarded. Work will begin on 6/22/2026.
- Temporary fencing and staging of materials will begin around May 20th for Johnson Park and Littlebrook. Test pits will begin on the upper section of the playground above the retaining walls for soil calculations on or about May 18.







