Princeton Middle School
Additions and Renovations
Project 5516B
Updates
- 10.30.2026 - Poured concrete slab and finished all utilities prep for the front addition.
![]()
|
![]()
|
- 10.23.2026 - Block A. Prep of the slab is underway. All underground utilities are completed. Stoning of the slab is complete. Radon is being installed.
![]()
|
![]()
|
- 10.16.2026 - Block A. The remaining storm is being installed at the new courtyard. Radon piping will begin. Slab is scheduled for early next week.
- 10.09.2026 - Block A underground sanitary and storm was completed and backfilled. New courtyard area was brought to grade and manholes raised to elevation.
![]()
|
![]()
|
- 10.01.2026 - Block A footings and foundation walls are completed. Backfilling was complete. New underground sanitary is being installed. All Leveling plates are set and grouted.
![]()
|
![]()
|
![]()
|
![]()
|
- 9.25.2026 - Block A footings are grouted. Backfilling is completed. New gas regulator and meter set installed.
![]()
|
![]()
|
- 9.18.2026 - Block A footings are 98% complete. Block walls are in progress. Grouting is complete in foundation block walls.
![]()
|
![]()
|
- 9.11.2026 - Block A footings are 98% complete. Block walls have begun. Base plates for steel were installed. All column piers have been completed.
![]()
|
![]()
|
![]()
|
![]() |
- 9.3.2026 - Block A footings are continuing.
![]()
|
![]()
|
- 8.27.2026 - Block A footings are continuing. Sports field will be hydro-seeded and strawed over.
![]()
|
![]()
|
- 8.21.2026 - New Block A footings are being installed. New Fire line has been installed and inspected. Underground storm utility has been completed. New Fiber has been installed.
![]()
|
![]()
|
![]()
|
![]()
|
- 8.15.2026 - Front building storm work is completed. Fire lines and water utility services are being installed to the new addition. The new parking ordinance has been approved by the Municipality, and signage is being made and installed.
- 8.06.2026 - Front building new courtyard storm sections are being installed. Building pad is complete. Footings have been laid out and will start next week. Sanitary has been installed.
|
|
![]()
|
- 7.31.2026 - Front building storm section is being installed. Detention basin is being shaped. Footings and foundations have been laid out and will begin next week.

- 7.23.2026 - Front building pad is being brought to sub-grade. Retention basin has been carved out, and shaping has begun. Storm utilities are being installed (sanitary and storm). A delivery of pipework and concrete structures has arrived.

- 7.17.2026 - Front Demolition: Topsoil was stripped back to allow for new building footprint.
Existing concrete was removed from the ground to allow for utility lines and building foundations.
- 7.10.2026 - Front Demolition: Sidewalks were removed. All existing light poles were removed along existing front pathway to school.
Rear Demolition: Parking lot was milled and sidewalks removed. Asphalt millings were removed
from site along with existing concrete. RCA was installed to level parking lot.

- 7.3.2026 - Heavy equipment was mobilized to the rear and front of school. Tracking pads were installed. Demolition began with the flagpole removal. Ground penetrating radar was used to locate all existing utilities in the rear of the bldg. Logistics plans are being generated.

- 6.26.2026 - Site contractor mobilized on 6.22.26 and installed construction fencing and signage. Both trailers were delivered. Milling machines will be arriving on 6.29.26 and will begin removal of back parking lot.

- 6.1.2026 - Notice of Acceptance (NOA) and contracts are being issued. Logistics plans were completed and work will begin 6/22/26.
- Pre-construction meetings are being held and logistics are being developed