7.10.2026 - Front Demolition: Sidewalks were removed. All existing light poles were removed along existing front pathway to school.
Rear Demolition: Parking lot was milled and sidewalks removed. Asphalt millings were removed
from site along with existing concrete. RCA was installed to level parking lot.
7.3.2026 - Heavy equipment was mobilized to the rear and front of school. Tracking pads were installed. Demolition began with the flagpole removal. Ground penetrating radar was used to locate all existing utilities in the rear of the bldg. Logistics plans are being generated.
6.26.2026 - Site contractor mobilized on 6.22.26 and installed construction fencing and signage. Both trailers were delivered. Milling machines will be arriving on 6.29.26 and will begin removal of back parking lot.
6.1.2026 - Notice of Acceptance (NOA) and contracts are being issued. Logistics plans were completed and work will begin 6/22/26.
Pre-construction meetings are being held and logistics are being developed