Project 5516A2

 

Updates

  • 7.10.2026 - Plumbing Demolition will be completed by next week. CMU Block was delivered.
PHS IT Demo progress
  • 7.3.2026 -  Demolition is continuing. Architect met with PHS staff to finalize color samples for the new space. 
5516A2 Demo Progress
  • 6.26.2026 - Demolition has begun with the block walls being removed.
5516A2 Demolition
5516A2 Demolition 3
  • 6.1.2026 - IT department renovation weekly meetings and site visits have been ongoing. Work will begin on 6/22/2026.
  • Site visit was held on 4/30/2026
  • Next site visit scheduled for 5/5/2026
  • Construction to begin 6/22/2026