Additions and Renovations

Project 5516D

Updates

  • 10.01.2026 - Vocal room concrete slab is complete. Foundations and piers of new south wing have forms, rebar and concrete pours ongoing. Retention basin excavation is nearing completion. Parking area partially completed for school staff use during construction.
walls

 

footings

 

  • 9.25.2026 - Footings for the Block B classrooms underway. Radon piping was completed at vocal room. New Slab was poured at vocal room. 
worksite

 

footing

 

  • 9.18.2026 - Footings for the Block B classrooms have begun. 
block b

 

block b

 

  • 9.11.2026 - New parking lot paving was installed and striped for parking spaces. Footings are being excavated on Block B for the large addition.
parking lot
  • 9.3.2026 - DGA was installed at new parking lot. Curbs at parking lot poured. Electrical conduit was placed for new parking lot lighting. 
curbs

 

dirt

 

  • 8.27.2026 - DGA was installed at new parking lot. Curbs at parking lot are being formed. Backfill was completed at vocal room foundations. Fencing is being altered for safety and egress for the staff and students. 
paved space
  • 8.21.2026 - New parking lot retaining wall has been installed. Back addition has been stacked out for footings. Parking lot is being brought to grade. Shed will be relocated. 
retaining wall

 

  • 8.15.2026 -  Block A vocal room has the footings completed and foundation walls are in place. 

    Grounding wires have been installed in footing. Underground utilities (storm and sanitary) have been installed. Parking lot retaining wall is being installed. Parking lot is being brought to subbase elevations. Conduits will be installed for new lighting at pole and dumpster area.

  • 8.06.2026 - Block A vocal / music room footings and columns have been poured with Anchor bolts and base plates. Block B large addition footings will begin next week.

LB New Footings

 

LB New Footings and Piers

 

  • 7.31.2026 - Sanitary piping has been installed. Storm piping is continuing, and outflow structures are being set at the retention basin. Footing began at small addition.
LB New Sanitation Piping
  • 7.23.2026 - Storm lines have been installed from building to retention basin. Retention basin was brought to sub-grade and shaped. Rear building pad for large addition was compaction tested.
LB building pad sub-grade
  • 7.17.2026 - New parking lot was leveled and set to sub-grade. Existing parking lot was removed and set to subgrade. The large addition area was excavated to allow for building pad and utilities and footings to begin.
  • 7.10.2026 - Site fence was installed. Demolition of existing storm water system was removed. Parking lot was milled to subgrade.
  • 7.3.2026 - Site fence was installed. Demolition of existing storm water system was removed. Demolition of the existing play set was completed in the rear of the building. Parking lot was milled to subgrade. 
5516D Site work

 

5516D site work

 

  • 6.26.2026 - Demolition began on Tuesday, 6.23.26. Milling machine was delivered and parking lot was milled. Existing fence was removed along with the basketball hoop.
LB 5516D Parking lot milling

 

LB 5516D Additional milling of parking lot

 

  • 6.1.12026 - Weekly meetings are progressing. Logistic plans were developed. Work will begin on 6/22/2026.
  • Pre-construction meetings are being held and logistics are being developed
  • Construction to begin 6/22/2026