7.10.2026 - Site fence was installed. Demolition of existing storm water system was removed. Parking lot was milled to subgrade.
7.3.2026 - Site fence was installed. Demolition of existing storm water system was removed. Demolition of the existing play set was completed in the rear of the building. Parking lot was milled to subgrade.
6.26.2026 - Demolition began on Tuesday, 6.23.26. Milling machine was delivered and parking lot was milled. Existing fence was removed along with the basketball hoop.
6.1.12026 - Weekly meetings are progressing. Logistic plans were developed. Work will begin on 6/22/2026.
Pre-construction meetings are being held and logistics are being developed