Community Park
Additions and Renovations

Project 5516C

Updates

  • 10.01.2026 - Prepping under slab utilities and prepping for slab pour in new gym.

slab pour

 

slab pour

 

  • 9.25.2026 - Back filling gym area. Working on electrical rough ins. Installing underground plumbing. Formwork and pouring piers in classroom addition. 

grouting

 

grouting hole

 

  • 9.18.2026 - Block walls for the stage are ongoing. Block walls are complete for the gym. Foundations for classrooms are ongoing. 

block walls

 

construction

 

  • 9.11.2026 - Foundation on New Gym is 90%. Working on the storage area steel. Under slab utilities have begun. Piers for the new classroom additions. 

blocka

 

blocka

 

construction pad

 

construction

 

  • 9.3.2026 - Footings, block walls, and grouting of walls completed.
ditch

 

constructions

 

  • 8.27.2026 - Poured foundations and footings. Began construction of black wall for the new gym area. 
cpconstruction

 

bulldozer

 

construction cp

 

footings

 

  • 8.21.2026 - Poured foundations and footings for New Gym area.
footings in gym area

 

footings

 

  • 8.15.2026 -  Poured footings for new columns in rooms 134/135. Mobilizing for new addition footings and foundations.
  • 8.06.2026 - Interior demolition of the second-floor resource room is complete. Temporary partition walls installed for second floor resource room. Rooms 134 and 135 floors saw cut and foundations have been located.
CP Elevated Addition Pad

 

CP 2nd Floor Partition Wall

  

  • 7.31.2026 - Interior demolition of the second-floor resource room is in progress. Compaction tests were completed for the building pads.
CP New Addition Pad
  • 7.23.2026 - Storm line to retention basin has been completed. Building pads will be proof rolled and compaction tested
CP Storm Line
CP Storm Line

 

  • 7.17.2026 - Storm piping continues from the front of the building to the retention pond. Additional storm lines will be installed.
  • 7.10.2026 - All drainage piping and storm structures were delivered, bioretention basin has begun.
    Building addition footprints have been set and topsoil removed. Installing new storm lines in rear of building.
 
CP Site work

 

CP Site Work

 

  • 7.3.2026 -  Courtyard and playground behind existing kindergarten classrooms are completely cleared away and graded for new concrete pads for each of the new additions.
  • First floor kindergarten classrooms were cleared out and made ready for installation of new footings. The existing Resource Room has been cleared to make way for demolition.
  • Digging for the bioretention basin has begun.
5516C Site Work
  • 6.26.2026 - Work started with site fencing and demolition of the courtyard. Tracking pad was installed.
CP Fencing 3

 

CP Fencing 1

 

CP 5516C Site Work 625-1

 

CP 5516C Site work

 

  • 6.1.2026 - Weekly meetings are progressing. Work will begin on 6/22/2026.
  • Pre-construction meetings are ongoing. 
  • Storage container was delivered 5/4/2026
  • Logistic plan was issued for temporary fence, storage containers, and all utilities
  • Construction to begin 6/22/2026