Branding

Utility Container

Community Park Additions and Renovations

Project 5516C

CP Media Center Rendering
CP Media Center Rendering
CP Outdoor Classroom Rendering
CP Outdoor Classroom Rendering
CP Outdoor Courtyard Rendering
CP Outdoor Courtyard Rendering
CP Outdoor Courtyard Rendering
CP Outdoor Courtyard Rendering
CP Outdoor Courtyard Rendering
CP Outdoor Courtyard Rendering
CP Library Courtyard Rendering
CP Library Courtyard Rendering
CP Exterior Rendering

Updates

  • 7.10.2026 - All drainage piping and storm structures were delivered, bioretention basin has begun.
    Building addition footprints have been set and topsoil removed. Installing new storm lines in rear of building.

 

CP Site work
  • 7.3.2026 -  Courtyard and playground behind existing kindergarten classrooms are completely cleared away and graded for new concrete pads for each of the new additions.
  • First floor kindergarten classrooms were cleared out and made ready for installation of new footings. The existing Resource Room has been cleared to make way for demolition.
  • Digging for the bioretention basin has begun.
 
CP Site work

 

CP Site Work

 

  • 6.26.2026 - Work started with site fencing and demolition of the courtyard. Tracking pad was installed.
CP Fencing 3

 

CP Fencing 1

 

CP 5516C Site Work 625-1

 

CP 5516C Site work

 

  • 6.1.2026 - Weekly meetings are progressing. Work will begin on 6/22/2026.
  • Pre-construction meetings are ongoing. 
  • Storage container was delivered 5/4/2026
  • Logistic plan was issued for temporary fence, storage containers, and all utilities
  • Construction to begin 6/22/2026